After residents’ protest, IBEDC moves to end 10-year power outage in Ibadan communities

5 months ago 13

The Ibadan Electricity Distribution Company (IBEDC) has outlined steps to resolve the 10-year power outage challenge in Iwo road – Lalupon communities in Ibadan.

IBEDC’s officer in charge of the Technical Unit, Christopher Lawal, made this known while addressing journalists on Wednesday.

He said part of the measures to be taken would include, but not limited to, placing 65 per cent of customers on the feeder who are currently receiving supply with 40 transformers on load shedding, while exploring options to back-feed some of the remaining distribution substations from an alternative feeder.

He explained that there would be extensive use of isolators with the existing network arrangement within a timeline of three weeks as well as cascading of load between feeders within a timeline of four weeks.

He added that Odo ori 11kv feeder will be converted to a 33kv feeder between an estimated period of eight to nine weeks as the medium-term solution.

He emphasised that IBEDC has held numerous meetings with community leaders to explain the situation and explore solutions.

Mr Lawal said that, in the long run, the construction of the 33Kv substation project in Lalupon, funded by the Central Bank of Nigeria (CBN), would completely resolve the ongoing power supply challenges in the area.

Article Page with Financial Support Promotion

Nigerians need credible journalism. Help us report it.

PREMIUM TIMES delivers fact-based journalism for Nigerians, by Nigerians — and our community of supporters, the readers who donate, make our work possible. Help us bring you and millions of others in-depth, meticulously researched news and information.

It’s essential to acknowledge that news production incurs expenses, and we take pride in never placing our stories behind a prohibitive paywall.

Will you support our newsroom with a modest donation to help maintain our commitment to free, accessible news?

“We sincerely apologise for the inconvenience caused by these challenges and are using this medium to assure our customers that every effort is being made to expedite the completion of the 33kV substation project and restore full power supply.

“As a customer-centric company, we are deeply concerned about the supply situation. As such, we have held over 10 meetings with the leaders of the communities to explain the situation. These meetings underscore our commitment to resolving these issues and improving service delivery,” he added.

Recall that PREMIUM TIMES reported that the residents of the communities, on Monday, staged a peaceful protest to the IBEDC office and Oyo State government secretariat in Agodi, Ibadan, where government representatives promised to intervene in the matter.



Support PREMIUM TIMES' journalism of integrity and credibility

At Premium Times, we firmly believe in the importance of high-quality journalism. Recognizing that not everyone can afford costly news subscriptions, we are dedicated to delivering meticulously researched, fact-checked news that remains freely accessible to all.

Whether you turn to Premium Times for daily updates, in-depth investigations into pressing national issues, or entertaining trending stories, we value your readership.

It’s essential to acknowledge that news production incurs expenses, and we take pride in never placing our stories behind a prohibitive paywall.

Would you consider supporting us with a modest contribution on a monthly basis to help maintain our commitment to free, accessible news? 

Make Contribution




TEXT AD: Call Willie - +2348098788999






PT Mag Campaign AD

Visit Source